The Goro nickel-cobalt mine is a fully integrated mining operation involving an open-pit mine, a processing plant and a port facility operated by Prony Resouces in the Southern Province of New Caledonia. The hydrometallurgical processing plant uses HPAL technology to produce nickel oxide, nickel hydroxide, cobalt carbonate and nickel hydroxide cake.
HPAL campaigns are currently limited by alunite and hematite scaling being produced at a faster rate than expected in the plant design. The thickness of scales cannot be measured during HPAL operations and HPAL must be stopped regularly for scales removal.
This scaling challenge significantly impacts production as an autoclave is stopped every three months for scales removal.
A solution is needed to extend and optimise the duration of HPAL campaigns by:
The solution must also fulfil the following requirements:
Challenge Launch Webinar
24th January 2023
EOI Submission Deadline
10th February 2023
Technical Briefing
20th March 2023
Pitch Sessions
3rd April 2023
Final Proposal Deadline
28th April 2023
The Global Mining Challenge is coordinated by Austmine and supported by the Australian Government Department of Industry, Science, Energy and Resources. The program provides new supply and export opportunities for opportunities for Australian METS companies and guides participants through a process of delivering solutions, technologies, and services to major international mining customers.